Development

 This is a basic page that talks about the process a developer has to go thru to get approval from the City of Asheville (COA) for their project and a little bit about the construction process as well.

Link to City of Asheville Development Services

Process for Level II, Level III, Conditional Zoning and Major Subdivision Review

1. Pre Application meeting with COA Technical Review Committee (TRC). This is not public at all.

2. Public Meeting with the surrounding neighborhood : the COA only requires notification of property owners within 200 feet of the proposed development so it pays to stay informed by other means.  WECAN has requested over the years that the neighborhood organizations also be notified which is now starting to happen.

3. Ten days after the Public Meeting, the developer can formally submit their application to TRC.  TRC meets the 1st and 3rd Mondays from 2 to 4pm as needed.  The public may watch these proceeding but there is no public comment allowed here.

4. Once the project has satisfied all of TRC's concerns, if the project is within the Central Business District or the River Arts District (or is a Hotel outside of those areas), and is considered a Major Works project, it must then go to the Design Review Committee which meets on the third Thursday of the month @ 12:30pm as needed.  This is a mandatory review but a voluntary compliance Committee... (the developer has to show up but does not have to do anything the committee recommends... except if they are horse trading for a Conditional Zoning project). The public may watch these proceedings and there is an opportunity for public comment as well. 

5. Then the project moves on to the COA Planning & Zoning Commission.  P&Z meets the first Wednesday of the month @ 5pm.  P&Z is an advisory commission to City Council... they vote up or down on a project but a no vote does not stop a project.  The public may watch these proceedings and there is an opportunity for public comment here too.  

5. And finally the project will be scheduled for a City Council Meeting, usually a month later.  The project is presented to City Council by the City Planning Staff member who has been assigned the project with staff recommendations given.  The applicant also has a chance to speak if they wish and City Council can ask questions of all of these folks. Then City Council will open the public comment section of the meeting to hear what everyone has to say and will then discuss the project amongst themselves and finally vote.  

There are cases where, if it sounds like the project is going to be turned down, City Council may chose to table the project.  If a project is rejected by City Council, it cannot re-apply for permits for 1 calendar year.... so sometimes to avoid this delay, a project is tabled so that the developer can make changes that might get a yes vote.

THE AVERY / PATTON 2 APARTMENTS


rendering from the middle of the intersection of Clingman and Hilliard


 This is a page for information about the Patton Place II Apartments being proposed for the north east corner of Clingman and Hilliard Avenues.


As of 11-20-21, this project has gone to its preliminary Design Review Meeting... and had its TRC meeting on Monday, Nov, 15, 2021 where it got an approval ... goes back to Design Review for its formal review on Dec 16th, 2021 @ 12:30pm and then on to P&Z on January 5, 2022 @ 5pm... And on March 9th, 2022 this project was approved by City Council


site plan
clingman avenue elevation
              
hilliard avenue elevation

timeline for their project with comments as to why it is a conditional zoning (CZ) project

Joe and i attended the Zoom Public Meeting on September 23rd, 2021 for the 196 unit "Patton 2" apartment complex last evening...here is a short synopsis:
196 apartments • 11,00 to 12,000 sq ft of commercial / retail / office space w/ 20 foot sidewalks along Hilliard • 190 to 200 parking spaces • north east corner of Clingman & Hilliard • mostly surface parking with garage under the Clingman Ave side of the main building • they expect 6 to 9 months to get to City Council • this is a CZ project • then 18 to 20 months of construction • same developer as Patton Place • photos below in order : site plan • Clingman Ave side • Hilliard side • their time line • because this project is technically in the Central Business District, it is required to take the additional step of going in front of Design Review that the HSCD project does not have to do... in case anyone wonders...


No comments:

Post a Comment

WECAN Board Meeting Minutes 4January 2024